Guides · Building safety

Remediation contribution orders: who ends up paying

The remediation provisions of the Building Safety Act 2022 are not a liability regime in the ordinary sense. They allocate a cost that has to fall somewhere, on a standard that owes very little to fault, and through a definition of who can be reached that was plainly drafted with corporate structuring in mind.

6 minute read · Building safety · England & Wales · ·

CaseLawDigest editorial team · how we write these

There is no cause of action to establish

A remediation contribution order requires a specified body corporate or partnership to make payments in connection with the remediation of relevant defects in a relevant building. The applicant does not have to establish negligence, breach of contract, breach of statutory duty, or any other cause of action against the respondent. It has to bring the respondent within a defined category, bring the building and the defect within the statutory definitions, and persuade the tribunal that an order would be just and equitable.

That last requirement carries the entire discretion, and it is the live battleground, because everything preceding it is definitional. Arguments that would be pleaded as a defence in ordinary litigation, that the respondent did not cause the defect, that others are more culpable, that the sum is disproportionate to the respondent’s involvement, arrive here as factors in a just and equitable assessment rather than as answers to a claim.

The commercial consequence is that the usual defensive architecture does not apply. Limitation as understood in contract and tort, contributory conduct, and the absence of any contractual nexus between applicant and respondent are not the obstacles they would otherwise be.

The associated person test defeats the structure

The reach of the regime comes from the breadth of association. It extends beyond the entity that developed or owns the building to persons associated with it, and the statutory test captures companies connected by common directors during a specified period, and companies where one controls the other.

This is the provision that matters most in practice, because it was aimed squarely at the special purpose vehicle. A development company that has been dissolved, stripped, or was never capitalised beyond the scheme it was built for, is not the end of the enquiry. The question becomes which solvent entities in the wider group fall within the association test during the relevant period, and those entities are exposed to an order for sums they never contracted for and may have had no operational involvement in.

The association test looks at a defined historical period, not at the group as it is structured today. Restructuring after the fact does not remove an entity that was associated when it mattered, which makes the corporate history of a development the first document to obtain and the hardest to reconstruct late.

Schedule 8 explains why these applications exist

The leaseholder protections limit what can be recovered through the service charge for relevant defects. Remediation still has to be paid for, so the cost that can no longer be passed to leaseholders has to be found elsewhere, and the contribution order is the mechanism by which it is redirected.

Reading the two parts together explains the pressure on the regime. A landlord facing remediation costs it cannot recover through the service charge has a strong commercial incentive to seek a contribution order against the developer and its associates, and applicants are not confined to leaseholders: interested persons include public bodies with their own reasons to bring proceedings.

Contribution orders and building liability orders are different instruments

They are frequently conflated and they do different things. A remediation contribution order is about money towards remediation of relevant defects, made by the tribunal on the just and equitable standard, with no need to establish liability. A building liability order operates on an existing relevant liability, and extends that liability to associated bodies corporate, so it presupposes a liability that has been or can be established and then follows it across the group.

The practical difference is what each requires you to prove. Where an underlying liability exists and the problem is that the entity holding it cannot pay, the building liability route addresses the problem directly. Where no underlying liability is realistically provable but the building falls within the regime, the contribution order is the route that does not require one. Choosing between them at the outset, rather than pleading towards both and committing to neither, is what distinguishes applications that resolve from those that do not.

This area is moving quickly through tribunal decisions on the meaning of relevant defect, building safety risk and the scope of the just and equitable discretion, so the statutory architecture set out here is the stable part rather than the whole picture.

Primary sources

The rule text this guide is written from. Rule numbers move, so check the date at the top of this page against the version you open.

More on statutory regimes

CaseLawDigest

See how these rules are being applied

CaseLawDigest reads every judgment published on Find Case Law for England and Wales, files it by practice area, and writes a summary a practitioner can use: what happened, what the court decided, and why. One weekly PDF per area, checked against the judgment before you see it.